pjcampbell_7243
Mar 23, 2010Cirrus
Manual fail over?
We have 2 BIG-IPs (BIG-IP 9.4.3 Build 1.4 Final ) setup in Active/Standby. We want to take down the secondary, and move it physically then let the secondary take over as primary so we can also move the primary.
If I click on "Force to standby" on my primary in the web interface under System -> High availability, will the secondary automatically take over?
Is there a better way to do this?
Also how quickly should I expect the secondary to take over.....